Sion foot overbridge inaugurated in Mumbai

The BMC said that the delay in construction of the FOB which began in January 2019 was due to Covid-19 , Shifting of underground utilities, Traffic Police Permission, Tree cutting permission, Change in methodology from Tubular truss to plate girder, cost variartion and escalator delivery.