Projects running behind schedule decline to 25-month low in February

In February, delayed central government projects declined to a 25-month low of 41.2%, while the cost overrun ratio dropped to a three-month low of 18.19%. With 1,902 projects monitored, 443 faced cost overruns and 764 experienced time overruns, with average delays exceeding 36 months for many projects. Railways and roads sectors were notably affected.